Typical projects:

  • 4 Lane Expressways

  • 100,000 to 300,000 m2

  • 50 mm depth

  • 20% new HMA Admix

  • 0.3% to 0.6% Rejuvenator​

Screenshot 2024-02-27 at 1.17.39 PM.png

Spring 2023 - Shaanxi Province - 225,000 M2

Hot In-Place Asphalt Recycling

Summer 2023 - Xianjuang Province - 260,000 M2

Hot In-Place Asphalt Recycling

Fall 2023 - Henan Province - 175,000 M2

Hot In-Place Asphalt Recyclng